Project Start Date: Thu 10/20/05
Project Finish Date: Fri 4/28/06
| ID | Task_Name | Duration | Start_Date | Finish_Date |
|---|---|---|---|---|
| 1 | Semester Starts | 1 day? | Tue 1/17/06 | Tue 1/17/06 |
| 2 | Inspect Parts | 2 days? | Tue 1/17/06 | Wed 1/18/06 |
| 3 | ELECTRICAL TESTING | 3 days? | Wed 1/18/06 | Fri 1/20/06 |
| 4 | Determine Current Draw of Motor | 1 day? | Wed 1/18/06 | Wed 1/18/06 |
| 5 | Determine Current Draw of CD Player | 3 days? | Wed 1/18/06 | Fri 1/20/06 |
| 6 | Determine Appropriate Power Supply | 1 day? | Fri 1/20/06 | Fri 1/20/06 |
| 7 | CHAIR ANALYSIS | 6 days? | Wed 1/18/06 | Mon 1/23/06 |
| 8 | Determine Reallife Centers of Mass to Compare with Experimental | 3 days? | Wed 1/18/06 | Fri 1/20/06 |
| 9 | Calculate Optimal Hinge Position | 3 days | Fri 1/20/06 | Sun 1/22/06 |
| 10 | Inspect Chair Frame Before Designing Reinforcements | 3 days | Fri 1/20/06 | Sun 1/22/06 |
| 11 | Determine Comfortable Rocking Displacement | 1 day | Mon 1/23/06 | Mon 1/23/06 |
| 12 | Determine Comfortable Rocking Speed | 1 day? | Mon 1/23/06 | Mon 1/23/06 |
| 13 | FRAME CONSTRUCTION | 35 days? | Mon 1/23/06 | Sun 2/26/06 |
| 14 | BASE FRAME CONSTRUCTION | 14 days | Thu 1/26/06 | Wed 2/8/06 |
| 15 | Finalize Base Design | 3 days | Thu 1/26/06 | Sat 1/28/06 |
| 16 | Construct 8020 | 2 days | Tue 2/7/06 | Wed 2/8/06 |
| 17 | CHAIR FRAME CONSTRUCTION | 23 days | Mon 1/23/06 | Tue 2/14/06 |
| 18 | Finalize Design of Internal Frame Reinforcements | 2 days | Mon 1/23/06 | Tue 1/24/06 |
| 19 | Cut Parts for Internal Frame | 3 days | Thu 2/9/06 | Sat 2/11/06 |
| 20 | Attach Frame to Rocker | 2 days | Mon 2/13/06 | Tue 2/14/06 |
| 21 | HINGE MECHANISM | 8 days? | Wed 2/15/06 | Wed 2/22/06 |
| 22 | Attach Reinforcements at Proper Location on Internal Chair Frame | 3 days | Wed 2/15/06 | Fri 2/17/06 |
| 23 | Assemble Hinge | 1 day? | Wed 2/15/06 | Wed 2/15/06 |
| 24 | Attach to Internal Frame at Optimal Location | 2 days | Wed 2/15/06 | Thu 2/16/06 |
| 25 | Attach bearing to hinge | 4 days | Sat 2/18/06 | Tue 2/21/06 |
| 26 | Attach Hinge Attachment onto Base | 2 days | Tue 2/21/06 | Wed 2/22/06 |
| 27 | Attach Hinge to Base | 2 days | Tue 2/21/06 | Wed 2/22/06 |
| 28 | SAFETY RISERS | 5 days? | Wed 2/22/06 | Sun 2/26/06 |
| 29 | Determine Maximum Forward Position | 1 day? | Wed 2/22/06 | Wed 2/22/06 |
| 30 | Cut Parts for Front Riser | 2 days | Wed 2/22/06 | Thu 2/23/06 |
| 31 | Attach Riser to Base | 2 days | Wed 2/22/06 | Thu 2/23/06 |
| 32 | Attach Riser Rest onto Chair Internal Frame | 2 days | Wed 2/22/06 | Thu 2/23/06 |
| 33 | Determine Maximum Recline Position | 1 day? | Fri 2/24/06 | Fri 2/24/06 |
| 34 | Cut Parts for Recline Riser | 3 days | Fri 2/24/06 | Sun 2/26/06 |
| 35 | Attach Recline Riser to Base | 3 days | Fri 2/24/06 | Sun 2/26/06 |
| 36 | Attach to Chair Frame | 2 days | Fri 2/24/06 | Sat 2/25/06 |
| 37 | ROCKING MECHANISM | 54 days? | Mon 1/30/06 | Fri 3/24/06 |
| 38 | ANALYSIS | 19 days? | Mon 2/13/06 | Fri 3/3/06 |
| 39 | Determine Optimal Linkage Bar Attachment Point | 2 days | Mon 2/13/06 | Tue 2/14/06 |
| 40 | Determine Optimal Motor Location | 2 days | Mon 2/13/06 | Tue 2/14/06 |
| 41 | Determine Optimal Cam Size | 6 days? | Sun 2/26/06 | Fri 3/3/06 |
| 42 | Determine Linkage Bar Length | 6 days? | Sun 2/26/06 | Fri 3/3/06 |
| 43 | CONSTRUCTION | 54 days? | Mon 1/30/06 | Fri 3/24/06 |
| 44 | Reinforce Internal Chair Frame at Linkage Bar Attachment Point | 12 days | Mon 2/27/06 | Fri 3/10/06 |
| 45 | Reinforce Base for Motor Attachment | 12 days | Mon 2/27/06 | Fri 3/10/06 |
| 46 | Attach Motor | 12 days? | Mon 2/27/06 | Fri 3/10/06 |
| 47 | SPEED Decreaser | 12 days? | Mon 1/30/06 | Fri 2/10/06 |
| 48 | Determine Mechanism | 5 days | Mon 1/30/06 | Fri 2/3/06 |
| 49 | Find Resistance | 5 days | Mon 1/30/06 | Fri 2/3/06 |
| 50 | Wire | 5 days? | Mon 1/30/06 | Fri 2/3/06 |
| 51 | Enclose | 5 days | Mon 2/6/06 | Fri 2/10/06 |
| 52 | CAM | 15 days? | Fri 3/3/06 | Fri 3/17/06 |
| 53 | Design Cam | 15 days | Fri 3/3/06 | Fri 3/17/06 |
| 54 | Construct Cam | 15 days | Fri 3/3/06 | Fri 3/17/06 |
| 55 | Attach to Motor | 15 days? | Fri 3/3/06 | Fri 3/17/06 |
| 56 | LINKAGE BAR | 8 days? | Fri 3/17/06 | Fri 3/24/06 |
| 57 | Design Linkage Bar | 8 days | Fri 3/17/06 | Fri 3/24/06 |
| 58 | Construct | 8 days? | Fri 3/17/06 | Fri 3/24/06 |
| 59 | Install Attachment Point onto Chair Frame | 8 days | Fri 3/17/06 | Fri 3/24/06 |
| 60 | Attach Linkage Bar | 8 days | Fri 3/17/06 | Fri 3/24/06 |
| 61 | Spring Break | 9 days | Sat 3/4/06 | Sun 3/12/06 |
| 62 | INITIAL ANALYSIS AND TESTING OF ROCKING MOTION | 3 days | Fri 3/24/06 | Sun 3/26/06 |
| 63 | Order Power Supply | 1 day? | Fri 3/24/06 | Fri 3/24/06 |
| 64 | ELECTRICAL | 75 days? | Mon 1/30/06 | Fri 4/14/06 |
| 65 | CONTROLS | 15 days? | Fri 3/24/06 | Fri 4/7/06 |
| 66 | CARETAKER CONTROL TOWER | 15 days | Fri 3/24/06 | Fri 4/7/06 |
| 67 | Design Control and CD Tower | 15 days | Fri 3/24/06 | Fri 4/7/06 |
| 68 | Cut Parts for Tower | 15 days | Fri 3/24/06 | Fri 4/7/06 |
| 69 | Construct Tower | 15 days | Fri 3/24/06 | Fri 4/7/06 |
| 70 | Attach to Base | 15 days | Fri 3/24/06 | Fri 4/7/06 |
| 71 | Install Switches | 15 days | Fri 3/24/06 | Fri 4/7/06 |
| 72 | USER CONTROL TOWER | 15 days? | Fri 3/24/06 | Fri 4/7/06 |
| 73 | Design User Control Tower | 15 days | Fri 3/24/06 | Fri 4/7/06 |
| 74 | Cut Parts | 15 days | Fri 3/24/06 | Fri 4/7/06 |
| 75 | Construct | 15 days | Fri 3/24/06 | Fri 4/7/06 |
| 76 | Attach to Frame | 15 days? | Fri 3/24/06 | Fri 4/7/06 |
| 77 | Construct Touch Pad Switch | 15 days | Fri 3/24/06 | Fri 4/7/06 |
| 78 | Optimize Purchased Squish Switch | 15 days | Fri 3/24/06 | Fri 4/7/06 |
| 79 | Install Switches | 15 days | Fri 3/24/06 | Fri 4/7/06 |
| 80 | AUDIO | 5 days | Sat 2/11/06 | Wed 2/15/06 |
| 81 | Install Speakers into Headrest | 4 days | Sat 2/11/06 | Tue 2/14/06 |
| 82 | Install CD Player into Control Tower | 3 days | Mon 2/13/06 | Wed 2/15/06 |
| 83 | WIRING | 75 days | Mon 1/30/06 | Fri 4/14/06 |
| 84 | Wire Switches | 8 days | Fri 4/7/06 | Fri 4/14/06 |
| 85 | Wire Motor | 75 days | Mon 1/30/06 | Fri 4/14/06 |
| 86 | Wire CD Player and Speakers | 75 days | Mon 1/30/06 | Fri 4/14/06 |
| 87 | Wire Power Supply | 3 days | Wed 4/12/06 | Fri 4/14/06 |
| 88 | ELECTRICAL TESTING | 3 days | Wed 4/12/06 | Fri 4/14/06 |
| 89 | FINAL CONSTRUCTION AND TESTING | 17 days | Wed 3/29/06 | Fri 4/14/06 |
| 90 | Run Full System Tests | 4 days | Wed 3/29/06 | Sat 4/1/06 |
| 91 | Patch Up Any Aesthetic Issues | 5 days | Sat 4/1/06 | Wed 4/5/06 |
| 92 | Cover Moving Parts | 5 days | Wed 4/5/06 | Sun 4/9/06 |
| 93 | Finalize Appearance | 5 days | Mon 4/10/06 | Fri 4/14/06 |
| 94 | End of Semester | 1 day? | Fri 4/28/06 | Fri 4/28/06 |